• LUCZORAMA SHIPWRECK SCAVENGER HUNT GIVEAWAY. 4 Weeks of Fun • 1 Legendary Prize ((OcCre’s Fram Ship)) • Global Crew Welcome!
    **VIEW THREAD HERE**

Build Log - Amerigo Vespucci - #1

Joined
Feb 21, 2025
Messages
17
Points
48

Location
Land O Lakes, Florida
Finally had a chance to upload the build log for the Amerigo Vespucci. Started in April, but had to travel a bit, so that slowed things down. This is second wood kit, and I an really enjoying it.
Also attached my personnel build log.
1752482706958.png1752482629546.png1752482634570.png
15 APR 2025 - Unpacked - Total hours: 1.0
I received the Amigo Vespucci kit from OcCre and couldn't wait to unpack it. The kit seemed complete and in good order, as usual.

1752482721173.png1752482731229.png1752482735363.png
21 APR 2025 - Labeled Parts - Total Hours: 2.5
Today, I labeled and organized the parts and reset the shipyard for the new production. I'm getting itchy to start, but I must finish the HMS Beagle first.

1752482764382.png1752482769452.png1752482773602.png
2 APR 2025 - Keel Laid - Total hours: 3.5
Big day! The keel was laid, and the frames cut out. Only had a little time before I had to get back to finishing the HMS Beagle.

1752482828103.png1752482832746.png1752482837163.png
10 MAY 2025 – Deck planking - Total Hours to Date: 15.0
Worked several hours on cutting and fitting the deck planks. Then, I started on the Deckhouse construction. Watertight doors and portholes were installed.

1752482883697.png1752482887787.png1752482892187.png
21JUN2025 - Rough planks - Total hours to date: 28.0
I wasn't able to work on this project for several weeks. I had to travel to Europe to conduct 3 surveys on the Clipper Cruise vessels. Ironically, one of them was the world's largest 5-masted square-rigged passenger sailing vessel. I took a lot of pictures and learned a lot. But now I am ready to get back to work on the Vespucci! I have completed the first course of planking. I also spent some time fairing the hull, even though it was just rough planking. Because the hull is steel, the planking will be covered with plaster and painted. So, I want the finished planks to be as smooth as possible. Plus, it is good practice for future projects.
1752482975762.png1752482980345.png1752482984528.png
27JUN2025 - 2nd Course of Planking - Total Hours: 36: hours
The 2nd course of planking is complete and ready for fairing with putty. The keel, aft deck, and framing rudder.

1752483057846.png1752483062765.png1752483066731.png
01 July 2025 - hull completed - Total hours: 45.0
The fairing and sanding are completed with one coat of primer. This took more time than expected, but the result should be good once fully painted. I will probably fill in a few more defects before starting the color coats.

1752483115576.png1752483119935.png1752483124262.png
14 July 2025 - hull painted and Portholes completed - Total hours: 65.0
Taping off the hull and getting the paint perfect was tough enough, but once completed, I had to drill holes for the portholes! That was nerve-racking. There are 96 portholes on each side, plus the side scuttles, which are next. It is starting to come together and look like a ship!
 

Attachments

Finally had a chance to upload the build log for the Amerigo Vespucci. Started in April, but had to travel a bit, so that slowed things down. This is second wood kit, and I an really enjoying it.
Also attached my personnel build log.
15 APR 2025 - Unpacked - Total hours: 1.0
I received the Amigo Vespucci kit from OcCre and couldn't wait to unpack it. The kit seemed complete and in good order, as usual.

21 APR 2025 - Labeled Parts - Total Hours: 2.5
Today, I labeled and organized the parts and reset the shipyard for the new production. I'm getting itchy to start, but I must finish the HMS Beagle first.

2 APR 2025 - Keel Laid - Total hours: 3.5
Big day! The keel was laid, and the frames cut out. Only had a little time before I had to get back to finishing the HMS Beagle.

10 MAY 2025 – Deck planking - Total Hours to Date: 15.0
Worked several hours on cutting and fitting the deck planks. Then, I started on the Deckhouse construction. Watertight doors and portholes were installed.

21JUN2025 - Rough planks - Total hours to date: 28.0
I wasn't able to work on this project for several weeks. I had to travel to Europe to conduct 3 surveys on the Clipper Cruise vessels. Ironically, one of them was the world's largest 5-masted square-rigged passenger sailing vessel. I took a lot of pictures and learned a lot. But now I am ready to get back to work on the Vespucci! I have completed the first course of planking. I also spent some time fairing the hull, even though it was just rough planking. Because the hull is steel, the planking will be covered with plaster and painted. So, I want the finished planks to be as smooth as possible. Plus, it is good practice for future projects.
27JUN2025 - 2nd Course of Planking - Total Hours: 36: hours
The 2nd course of planking is complete and ready for fairing with putty. The keel, aft deck, and framing rudder.

01 July 2025 - hull completed - Total hours: 45.0
The fairing and sanding are completed with one coat of primer. This took more time than expected, but the result should be good once fully painted. I will probably fill in a few more defects before starting the color coats.

14 July 2025 - hull painted and Portholes completed - Total hours: 65.0
Taping off the hull and getting the paint perfect was tough enough, but once completed, I had to drill holes for the portholes! That was nerve-racking. There are 96 portholes on each side, plus the side scuttles, which are next. It is starting to come together and look like a ship!
Hello Charlie
Nice progress so far on the hull.
I built the AV last year (my build log is on SoS should you be interested)
Cheers
 
Back
Top