The last wale plank installed, small issues corrected and sanded in place.
The forecastle deck was also glued in place and secured with rubber bands. For rubber bands to hold, I drove one nail into hull and use it to hold the stretched bands.
Once wale was dried and secured on the hull I started marking the right-hand end of fenders.
The only one marking that is showing left-hand side of a fender is between second and third water openings. This area has to have a shorter span between two fenders. Not sure if this is historically correct but, hey, no completelly accurate plans for SM exists...If there is any plan to be proven, I will build another SM from scratch...So, lets back to business of placing fenders...
Plank 1x3mm was used for this work. Individual planks were cut and fitting was done by sanding and testing each one so they will sit tight between wales. The second run of fenders will cover them as well as wales. The third fender will do the same as second layer. Excess CA glue will be removed after but will try not to mess it too much..
There is no specific order, I just decided to run all 'upper' fenders first..
There is also a layer of veneer put on the rudder area...
The second fender layer started... before adding the second layer, the wales and fenders will have to be flattened by sending so the second layer will fit in smoothly, no bumps, otherwise the two 1x3mm planks (first and second layer) will show where they are connected (glued).
That was all for this evening... happy modelling.
The forecastle deck was also glued in place and secured with rubber bands. For rubber bands to hold, I drove one nail into hull and use it to hold the stretched bands.
Once wale was dried and secured on the hull I started marking the right-hand end of fenders.
The only one marking that is showing left-hand side of a fender is between second and third water openings. This area has to have a shorter span between two fenders. Not sure if this is historically correct but, hey, no completelly accurate plans for SM exists...If there is any plan to be proven, I will build another SM from scratch...So, lets back to business of placing fenders...
Plank 1x3mm was used for this work. Individual planks were cut and fitting was done by sanding and testing each one so they will sit tight between wales. The second run of fenders will cover them as well as wales. The third fender will do the same as second layer. Excess CA glue will be removed after but will try not to mess it too much..
There is no specific order, I just decided to run all 'upper' fenders first..
There is also a layer of veneer put on the rudder area...
The second fender layer started... before adding the second layer, the wales and fenders will have to be flattened by sending so the second layer will fit in smoothly, no bumps, otherwise the two 1x3mm planks (first and second layer) will show where they are connected (glued).
That was all for this evening... happy modelling.